Tower Grove Park was established in 1872. Its original plan included a stream that flowed continuously from south to north across the east end of the park. In 1910, that stream was buried — routed into an underground pipe and removed from the park’s landscape for over a century. The Nee Lee Nee project brought it back.
Daylighting a stream that has been underground for 100 years inside a National Historic Landmark is a technical challenge of significant complexity. The design team coordinated with the National Park Service throughout, ensuring that every element of the new stream design respected the park’s historic character and the integrity of the 1870s-era bridges through which the stream now flows. The new alignment closely mimics the original 1876 stream path — threading beneath five of the park’s historic stone bridges as if it had never left.
Client
Tower Grove Park
Size
3 AC / 43-Acre Watershed
Photography
Gaparazzi
Markets
Parks & Open Space
Civic and Cultural

01 / THE GAP
A buried waterway within a historic park
Tower Grove Park sought to restore a stream piped underground in 1910.
This historic stream had been buried in an underground pipe network since 1910. For over a century, a 43-acre watershed drained into the combined sewer system rather than flowing through the park as it was designed to do. The absence of the stream was an ecological loss and a cultural one.

02 / THE SEED
Restoring the alignment with historic and tribal guidance
The team followed the stream’s 1876 alignment beneath five historic bridges.


The project was developed in partnership with the Osage Nation, whose people were the original inhabitants of this land. Tribal guidance shaped the design process, and tribal artists have since worked with the park and the design team to develop animal depictions for future integration into the landscape. An ongoing relationship has been formed — one that extends beyond the project itself.
The stream closely mimics the stream’s original 1876 alignment while integrating bridge crossings, pathways, bioretention areas, nature play, and outdoor educational spaces. Five of the park’s 1870s-era bridges were threaded into the new stream alignment.

03 / THE SPROUT
Stormwater management within a restored stream
The project records completion in March 2022.
The stream and bioretention system are reported to retain 3.8 million gallons annually from the 43-acre watershed. Green infrastructure grants provided $1.4 million in support. The park’s partnership with the Osage Nation extends beyond construction.


COMMUNITY INPUT
An ongoing partnership with the Osage Nation
Park and design team have continued working with tribal artists on animal depictions for integration into the landscape. National Park Service coordination addressed historic preservation requirements



Project by the Numbers
Details
Collaborators
Architecture
LJC Design and Engineering
Engagement
Osage Nation
Landscape contractor
DJM Ecological
Photography
Gaparazzi
Additional
National Park Service, Metropolitan Sewer District of St. Louis
Acknowledgement
Work Completed by the Kanopi Gap team while Employed at LJC Design & Engineering